In which of the following phases in Lewin's planned change process is it important to evaluate results, provide feedback to the people involved, and make any required modifications in the original change?
A) Unfreezing phase
B) Structuring phase
C) Refreezing phase
D) Improvising phase
E) Coercing phase
Correct Answer: