Solved

If the Sum of the Task Times Required to Produce

Question 19

True/False

If the sum of the task times required to produce a product is 45 minutes and the cycle time for the same product is 10 minutes, the theoretical minimum number of workstations is 5 using the assembly-line balancing procedure.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions