Multiple Choice
In a work center, Machine A has a 10-minute set-up time per batch and a 2-minute per unit run time. Machine B performs the identical function but has a set-up time of 30 minutes and a 1-minute run time per unit. The work center makes products in batches ranging from 1 unit to 100 units. Assuming capacity is not a limitation on either Machine, in order to minimize the total processing time, on which batches should Machine B be used?
A) All batches should be run on Machine B.
B) Batches of more than 20 units should be run on Machine B.
C) Batches of fewer than 80 units should be run on Machine B.
D) Batches with up to 50 units should be run on Machine B.
E) No batches should be run on Machine B.
Correct Answer:

Verified
Correct Answer:
Verified
Q9: Which of the following is not a
Q10: Assemble-to-order means moving the customer order decoupling
Q11: This tool defines how parts go together,
Q12: The product-process matrix shows the relationship between
Q13: The focus in the make-to-stock environment is
Q15: A process flowchart denotes what happens to
Q17: Assume a fixed cost for a process
Q18: In studying positioning of inventory in supply
Q19: One methodology used to evaluate equipment investment
Q48: The term "assembly line" refers to progressive