Multiple Choice
In studying the product-process matrix describing layout strategies, which of the following is most appropriate?
I. As you move from project to manufacturing cell to continuous process, product volume increases while standardization increases.
II. As you move from project to manufacturing cell to continuous process, product volume decreases while standardization decreases.
III. As you move from project to manufacturing cell to continuous process, product volume increases while standardization decreases.
IV. As you move from project to manufacturing cell to continuous process, product volume decreases while standardization increases.
A) I
B) II
C) III
D) IV
E) I and II
Correct Answer:

Verified
Correct Answer:
Verified
Q1: Work-center layouts allocate dissimilar machines into cells
Q2: A production environment where the customer is
Q4: Break-even analysis can be used to help
Q5: Having stamping and drill press departments would
Q6: Suppose that you have two processes A
Q7: You are hired as a consultant to
Q8: Which of the following tend to have
Q9: Which of the following is not a
Q10: Assemble-to-order means moving the customer order decoupling
Q11: This tool defines how parts go together,