The 10th Repetition of Job Is Timed at 100 Minutes

Question 38

Multiple Choice

The 10th repetition of job is timed at 100 minutes. If the learning curve for this job is 80 percent, what is the estimated time for the 100th repetition of this job?


A) 47.66 minutes
B) 62.50 minutes
C) 80 minutes
D) 92.50 minutes
E) 100 minutes