Multiple Choice
This is a further subdivision of a project. It is usually not longer than several months in duration and is performed by one group or organization.
A) Work package
B) Work breakdown structure
C) Project milestone
D) Task
E) Statement of work
Correct Answer:

Verified
Correct Answer:
Verified