Multiple Choice
A project has four activities: A, B, C, and D. The amount spent on each activity to date is $22K, $14K, $12K, and $28K respectively. The planned percentages complete for the current date are 90%, 80%, 70%, and 20% respectively. The actual percentages complete for the current date are 100%, 90%, 75%, and 10% respectively. The actual cost of the work performed to date is $40K. What is the BCWP for Activity A?
A) $0 − $5K
B) $5.01K − $10K
C) $10.01K − $15K
D) $15.01K − $20K
E) Over $20K
Correct Answer:

Verified
Correct Answer:
Verified
Q43: In a Gantt chart, the horizontal axis
Q44: Upper-level management must decide between pure, functional,
Q45: If a single estimate of the time
Q46: Which of the following is not a
Q47: One of the disadvantages of a pure
Q49: The fact that organizations are flattening is
Q50: A group of activities combined to be
Q51: A tracking Gantt chart superimposes the current
Q52: You have just used the network planning
Q53: A simple project listing of five activities