Multiple Choice
For a low-volume job shop type of manufacturing, which of the following is the typical production scheduling approach?
A) Finite forward scheduling
B) Finite backward scheduling
C) Infinite backward scheduling
D) Infinite forward scheduling
E) Soonest due date
Correct Answer:

Verified