Multiple Choice
Which of the following priority rules used in scheduling the sequence of production is calculated as the time remaining before the due date minus the remaining processing time, with the smallest value being run first?
A) STR
B) CR
C) SOT
D) LCFS
E) EDD
Correct Answer:

Verified
Correct Answer:
Verified