Multiple Choice
The assignment method is useful in solving scheduling problems that have which of the following characteristics?
A) There are n jobs to be distributed to n machines or workers.
B) Each job can only be done on one particular machine.
C) Speed and efficiency are important.
D) The objective is to minimize cost and lateness of delivery.
E) The jobs have to go through more than one process.