Multiple Choice
Assume you are sequencing jobs using Johnson's rule. There are three jobs called A, B, and C. The first step is assembling and the second step is painting. Job A requires 3 hours to assemble and 6 hours to paint. Job B requires 7 hours to assemble and 2 hours to paint. Job C requires 4 hours to assemble and 1 hour to paint. The objective is to minimize the total processing time of all jobs, using Johnson's rule. What is the completion time of the last job in the sequence in the second step (painting) ?
A) 14
B) 15
C) 9
D) 12
E) 10
Correct Answer:

Verified
Correct Answer:
Verified
Q1: The term "dependent events" refers to a
Q2: For a continuous-process type of manufacturing, which
Q3: Assume you are sequencing jobs using Johnson's
Q4: According to the theory of constraints, a
Q5: Most process are both labor- and machine-limited.
Q7: Since there are so many nonbottleneck operations,
Q8: When work is scheduled in detail using
Q9: Which of the following is not a
Q10: In a process sequence where a product
Q11: A job has 10 days of processing