Multiple Choice
Which of the following is considered a primary report in an MRP system?
A) Planned-order schedule
B) Peg report
C) Planning report
D) Inventory accuracy report
E) Aggregate production plan report
Correct Answer:

Verified
Correct Answer:
Verified