Which of the following is the planned-order release using an MRP program if the gross requirement is 5,000, inventory on hand is 1,200, and planned receipts are 800?
A) 7,000
B) 4,200
C) 3,000
D) 2,000
E) 1,200
Correct Answer:

Verified
Correct Answer: