In an MRP problem, A is an MPS item. Every A requires 2 B's and 3 C's. Every B requires 5 C's. All lead times are two periods. Initial inventory value for A is 100, B is 200, and C is 0. Use lot-4-lot method for order quantities for all items. If gross requirement for A is 800 in period 9, what will be the planned-order release for B in period 5?
A) 1,600
B) 1,400
C) 700
D) 800
E) 1,200
Correct Answer: