Multiple Choice
A project charter consists of:
A) a description of the nonfinancial benefits to flow from the project, a list of the key outputs to be produced and an analysis of the stakeholders of the project and their expectations.
B) a list of the milestones and expected timing.
C) a definition of the work that needs to be undertaken to achieve the project, its scope, and specific exclusions.
D) All of the above