Multiple Choice
Table H.1
A worker was observed for four cycles in a repetitive task that contains four distinct elements. The observer recorded the following items in seconds, using the snap-back method:
-The observer assigned a performance rating factor of 1.15 to the worker and the company employs an allowance factor of 20%. How many more observations must be made in order to develop an estimate of the select time for Element 4 that is within 5% with 95% accuracy?
A) 1
B) 3
C) 5
D) 7