Multiple Choice
A single-sampling plan by attributes is needed for a purchased component. Given the following information, what is the producer's risk? Table G.1 is appended to this exam. Sample size = 75
Acceptance number (c) = 3
Acceptance quality level (AQL) = 0.01
Lot tolerance proportion defective (LTPD) = 0.04
A) .007
B) .008
C) .009
D) .010
Correct Answer:

Verified
Correct Answer:
Verified
Q72: A quality manager has established a sampling
Q73: Use Table G.1 for the following question.
Q74: Which of the following is an example
Q75: A double-sampling plan has n₁ = 50,
Q76: This OC curve represents a sampling plan
Q78: A single-sampling plan by attributes is needed
Q79: The AOQL is the highest point in
Q80: This OC curve represents a sampling plan
Q81: Replacing all defective items in a rejected
Q82: The lot tolerance proportion defective (LTPD) is