Solved

The Production Rate Has Been Steady at 20 Units Per

Question 21

Multiple Choice

The production rate has been steady at 20 units per hour. The average work-in-process inventory at this station is 15 units. What is the average lead time through this manufacturing station?


A) 15 minutes
B) 30 minutes
C) 45 minutes
D) 1.0 hours

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge