Multiple Choice
When choosing a priority sequencing rule:
A) select multiple-dimension rules because they dominate single-dimension rules for all performance measures.
B) always select the rule that minimizes the amount of past-due jobs.
C) test a variety of rules before making a decision.
D) select CR or S/RO because they use more information.
Correct Answer:

Verified
Correct Answer:
Verified