Multiple Choice
Determining a production sequence for a group of jobs in a two-station flow shop to minimize the makespan has the advantage of:
A) maximizing the utilization of the shop.
B) minimizing the percentage of jobs past due.
C) minimizing the flow time of jobs on the first machine.
D) minimizing the variance of past-due hours.