Multiple Choice
Table 1.2
The Abco Company manufactures electrical assemblies. The current process uses 10 workers and produces 200 units per hour. You are considering changing the process with new assembly methods that increase output to 300 units per hour, but will require 14 workers. Particulars are as follows:
Workers are paid at a rate of $10 per hour, and overhead is charged at 140% (or 1.4 times) labor costs. Finished switches sell for $20 / unit.
-Use the information provided in Table 1.2. Based on your productivity calculations, what decision should you make?
A) implement the new process
B) stay with the current process
C) need more information to make a decision
D) Either process is acceptable (since the multi-factor productivities are the same) .
Correct Answer:

Verified
Correct Answer:
Verified
Q97: A set of activities that delivers value
Q98: Table 1.1<br>You are the Production Manager for
Q99: Which of the following is an example
Q100: While other suppliers bidding for the contract
Q101: Flexibility is a possible competitive priority.
Q103: A company's ability to support varying rates
Q104: Operations management refers to the systematic design,
Q105: Explain what an operations strategy is and
Q106: With regards to globalized operations and cost
Q107: The framework for carrying out all of