Multiple Choice
A standard work year is 2,000 hours at the Luther Mill and it takes about an hour and a half to fill a customer order. Last year saw 15,000 customer orders at the mill and the manager has a new John Deere in mind as a company car, so he hopes that there is an increase of 15% in customer orders for next year. If the manager hires fourteen workers, what is the capacity cushion?
A) 7.6%
B) 8.2%
C) 6.9%
D) 8.8%
Correct Answer:

Verified
Correct Answer:
Verified
Q107: Figure 4.1<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Figure 4.1
Q108: A larger capacity cushion can help firms
Q109: If demand is increasing, and you also
Q110: A wait-and-see capacity strategy:<br>A) involves small, frequent
Q111: Utilization is the degree to which equipment,
Q113: When a firm makes a long-term capacity
Q114: Extremely complex service capacity problems for which
Q115: A larger capacity cushion may be required
Q116: The capacity requirement for a year's output
Q117: A process's capacity requirement states the future