Multiple Choice
Scenario 4.7
The B. Sharp Company has a rapidly growing product line that requires two work centers, X and Y for manufacture. Work Center X has a current capacity of 50,000 units per year, and Work Center Y is capable of 55,000 units per year. This year (year 0) , sales of the product line are expected to reach 50,000 units. Growth is projected at an additional 3,000 units each year through year 3. Pre-tax profits are expected to be $60 per unit throughout the 3-year planning period. Two alternatives are being considered:1) Expand both Work Centers X and Y at the end of year 0 to a capacity of 60,000 units per year, at a total cost for both Work Centers of $500,000;
2) Expand Work Center X at the end of year 0 to 55,000 units per year, matching Work Center Y, at a cost of $300,000, then expanding both Work Centers to 60,000 units per year at the end of year 2, at an additional cost at that time of $350,000.
The Sharp Company will not consider projects that don't show a 3rd year positive net present value using a discount rate of 20%.
-Use the information in Scenario 4.7. What is the pre-tax cash flow (net present value) for alternative #1 compared to the base case of doing nothing for the next five years?
A) negative pre-tax cash flow
B) more than $0 but less than $100,000
C) more than $100,000 but less than $200,000
D) more than $200,000
Correct Answer:

Verified
Correct Answer:
Verified
Q91: The _ concept states that the average
Q92: Capacity planning requires a demand forecast for
Q93: Table 4.1<br>The Union Manufacturing Company is producing
Q94: Larry's Wickets, Inc. is producing two types
Q95: A firm may preempt the expansion of
Q97: The seven-person maintenance function at a hospital
Q98: Long-term capacity decisions that confront managers include
Q99: What are the four steps involved in
Q100: A capacity decision in a call center,
Q101: A capacity cushion is the amount of