Multiple Choice
The third step in Theory of Constraints application, "subordinate all other decisions to Step 2," means that the analyst should:
A) wait for authorization before proceeding with any system-wide changes.
B) schedule non-bottleneck resources to support the bottleneck schedule.
C) seek to increase capacity of only the bottleneck resources.
D) seek to increase capacity of both the bottleneck and non-bottleneck resources.
Correct Answer:

Verified
Correct Answer:
Verified
Q1: Which one of the following statements about
Q2: The production of a particular product consists
Q4: How can Theory of Constraints principles be
Q5: Figure 5.2<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Figure 5.2
Q6: Table 5.2<br>A company makes four products that
Q7: Table 5.2<br>A company makes four products that
Q8: Table 5.2<br>A company makes four products that
Q9: Any factor that limits the performance of
Q10: Describe three ways that line balancing and
Q11: Schmidt Industries makes four different snake traps;