Multiple Choice
Figure 5.4
-Use the information in Figure 5.4. If each task has a work time of one minute and there are 480 work minutes in a day, what is the task assignment at the fourth workstation if maximum output is desired?
A) A
B) B
C) C
D) D
Correct Answer: