Multiple Choice
Table 5.4
The Superior Management Company assembles muffalettas in The Big Easy. The steps to making a world class sandwich and the time required (in seconds) for each step are shown in the table.
-Customers demand muffalettas at the rate of 20 sandwiches per hour. Use the information in Table 5.4 to determine the cycle time that will meet this level of demand.
A) 100 seconds
B) 120 seconds
C) 180 seconds
D) 240 seconds