Consider the following production process. It is trying to meet a market demand of 250 units per week.
Step 1: Material release schedule
Step 2: Drilling (capacity is 300 units/week)
Step 3: Tapping (capacity is 150 units/week)
Step 4: Grinding (capacity is 300 units/week)
Step 5: Coating (capacity is 200 units/week)
Step 6: Inspection (capacity is 500 units/week)
a. Where should buffers be placed?
b. Which resource is the drum?
c. Where should the rope be placed?
d. Which resource is the bottleneck?
e. Which resource is the CCR?
Correct Answer:

Verified
a. A constraint buffer should be placed ...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q22: Explain why a bottleneck limits system output.
Q23: Table 5.2<br>A company makes four products that
Q24: Table 5.4<br>The Superior Management Company assembles muffalettas
Q25: Table 5.1<br>A company makes four products that
Q26: Table 5.3<br>King Supply makes four different types
Q28: Which of the following statements concerning line
Q29: To generate the maximum output, the cycle
Q30: Figure 5.3<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Figure 5.3
Q31: Regardless of the number of tasks or
Q32: Table 5.2<br>A company makes four products that