    The Production of 240 Units During a 480-Minute Work Shift
Solved

The Production of 240 Units During a 480-Minute Work Shift

Question 69

Question 69

Multiple Choice

The production of 240 units during a 480-minute work shift results in a takt time of:


A) 24 seconds.
B) 30 seconds.
C) 120 seconds.
D) 240 seconds.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q64: Five S practices can enable workers to

Q65: In a lean system, large inventories are

Q66: The just-in-time (JIT) philosophy is the belief

Q67: Describe the process considerations organizations must evaluate

Q68: Which of the following statements about the

Q70: Lean systems try to:<br>A) produce a product

Q71: Briefly outline the steps to be followed

Q72: A Kanban is a card used to

Q73: An item sells at a rate of

Q74: Briefly discuss the House of Toyota, including

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines