    The Production of 150 Units During a 480-Minute Work Shift
Solved

The Production of 150 Units During a 480-Minute Work Shift

Question 61

Question 61

Multiple Choice

The production of 150 units during a 480-minute work shift results in a takt time of:


A) 150 seconds.
B) 192 seconds.
C) 120 seconds.
D) 18.8 seconds.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q56: The just-in-time (JIT) system is a(n):<br>A) management

Q57: Group technology collects similar parts into families

Q58: If frequent, small shipments of purchased items

Q59: _ is a methodology consisting of five

Q60: In lean systems, the need for single-digit

Q62: In a lean system, the key to

Q63: Scenario 6.1<br>El Gran Raton, the producers of

Q64: Five S practices can enable workers to

Q65: In a lean system, large inventories are

Q66: The just-in-time (JIT) philosophy is the belief

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines