An Item Sells at a Rate of 600 Units Per

Question 14

Essay

An item sells at a rate of 600 units per day. If a plant works two shifts per day (480 minutes each shift), what takt time is required for the plant to meet this demand?

Correct Answer:

verifed

Verified

480 minutes per shift × 2 shif...