At Eady Corporation, Maintenance Is a Variable Overhead Cost That

Question 212

Multiple Choice

At Eady Corporation, maintenance is a variable overhead cost that is based on machine-hours. The performance report for July showed that actual maintenance costs totaled $8,650 and that the associated rate variance was $250 unfavorable. If 5,000 machine-hours were actually worked during July, the standard maintenance cost per machine-hour was:


A) $1.73 per machine-hour
B) $1.78 per machine-hour
C) $1.68 per machine-hour
D) $1.83 per machine-hour