Multiple Choice
A company could add $10,000 per week in revenues if the project depicted in Table 7.10 could be shortened.
Table 7.10
Four possible options exist to crash activities: crash A by one week at a cost of $6,000; crash C by two weeks at a cost of $15,000; crash E by one week at a cost of $2,000; and crash I one week at a cost of $7,000. What is the maximum amount of additional profit that can be made by crashing an option (or options) ?
A) less than or equal to $4,000
B) greater than $4,000 but less than or equal to $8,000
C) greater than $8,000 but less than or equal to $12,000
D) greater than $12,000
Correct Answer:

Verified
Correct Answer:
Verified
Q59: A Gantt chart is a project schedule
Q60: Assume that activity G has the following
Q61: A plan that identifies key threats to
Q62: The earliest start time is never the
Q63: Phoebe B. Beebee is constructing a canal
Q65: The following table contains a list of
Q66: In addition to finishing the work, the
Q67: Table 7.5<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table 7.5
Q68: Table 7.9<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table 7.9
Q69: The _ is a statement of all