Multiple Choice
Table 7.10
Four possible options exist to crash activities: crash A by one week at a cost of $6,000; crash C by two weeks at a cost of $15,000; crash E by one week at a cost of $2,000; and crash I one week at a cost of $7,000. What is the maximum amount of additional profit that can be made by crashing an option (or options) ?
A) less than or equal to $4,000
B) greater than $4,000 but less than or equal to $8,000
C) greater than $8,000 but less than or equal to $12,000
D) greater than $12,000
-If a project has exactly one critical path, which of the following statements is True?
A) Crashing an activity on the critical path will always result in an increase in total project profits.
B) Activities on the critical path cannot be crashed.
C) Crashing an activity on the critical path will always result in a reduced total project completion time.
D) The best schedule is one in which all activities are crashed as much as possible.
Correct Answer:

Verified
Correct Answer:
Verified
Q129: A project has three paths. A-B-C has
Q130: Table 7.9<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table 7.9
Q131: Figure to accompany Table 7.7<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg"
Q132: Table 7.14<br>You are responsible for managing a
Q133: A good risk management plan will contain
Q134: Table 7.4<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table 7.4
Q135: Table 7.5<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table 7.5
Q136: In making an estimate of the most
Q137: Table 7.6<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table 7.6
Q139: Table 7.4<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table 7.4