    Following Are Four Sets of Most Optimistic, Most Likely, and Most
Solved

Following Are Four Sets of Most Optimistic, Most Likely, and Most

Question 81

Question 81

Multiple Choice

Following are four sets of most optimistic, most likely, and most pessimistic times (in weeks) for an activity. Which one of the four sets will have a mean estimated time equal to the most likely time?


A) 1, 9, 9
B) 1, 5, 9
C) 1, 1, 9
D) 1, 5, 5

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q76: Activity slack is defined as:<br>A) latest start

Q77: Table 7.13<br>All activity times for the project

Q78: The _ is the shortest time in

Q79: A pure project organizational structure houses the

Q80: Table 7.3<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table 7.3

Q82: What characteristics should be considered when selecting

Q83: Figure to accompany Table 7.1<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg"

Q84: Figure to accompany Table 7.7<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg"

Q85: The optimistic time is the probable time

Q86: Table 7.2<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table 7.2

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines