Multiple Choice
To calculate the probability of completing a project by a certain date:
A) the expected completion time of the project is taken to be the sum of the activity times on the shortest path.
B) the variance of the distribution of project completion times is taken to be one-sixth the difference between the latest finish time and the earliest finish time of the last activity in the project.
C) we assume that the activity durations are independent of each other so that the normal distribution can be used.
D) we need only the parameters of the beta distribution for the finish node of the diagram.
Correct Answer:

Verified
Correct Answer:
Verified
Q117: Projects, and the application of project management,
Q118: Assuming a beta distribution is being used,
Q119: Table 7.2<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table 7.2
Q120: Why do managers want to know the
Q121: A(n) _ is an interrelated set of
Q123: You are given the following information about
Q124: Table 7.5<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table 7.5
Q125: A relationship that determines the sequence for
Q126: The earliest start time for an activity
Q127: Figure to accompany Table 7.7<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg"