Multiple Choice
Table 7.14
You are responsible for managing a project with the following activities (times are given in weeks) .
-Using Table 7.14, if the expected time for activity C is changed to 12 weeks, by how many weeks will the project's expected completion time increase?
A) It will not change.
B) It will increase by one week.
C) It will increase by two weeks.
D) It will increase by three weeks.
Correct Answer:

Verified
Correct Answer:
Verified
Q1: To find the standard deviation of the
Q2: Figure to accompany Table 7.1<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg"
Q3: Figure to accompany Table 7.1<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg"
Q5: The _ is determined by starting with
Q6: Table 7.6<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table 7.6
Q7: Project managers should be able to organize
Q8: Table 7.5<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table 7.5
Q9: Figure to accompany Table 7.7<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg"
Q10: Table 7.8<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table 7.8
Q11: Table 7.4<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table 7.4