You are responsible for managing a project with the following activities (times are given in weeks) .
Table 7.14 You are responsible for managing a project with the following activities (times are given in weeks) .    -Using Table 7.14, if the expected time for activity C is changed to 12 weeks, by how many weeks will the project's expected completion time increase? A)  It will not change. B)  It will increase by one week. C)  It will increase by two weeks. D)  It will increase by three weeks.
-Using Table 7.14, if the expected time for activity C is changed to 12 weeks, by how many weeks will the project's expected completion time increase?


A) It will not change.
B) It will increase by one week.
C) It will increase by two weeks.
D) It will increase by three weeks.