Essay
Consider the activities, durations, and predecessor relationships in the following network. Draw the network and answer the questions that follow.
a. What is the expected time for activity B?
b. What is the variance for activity B?
c. Based on the calculation of estimated times, what is the critical path?
d. What is the estimated time of the critical path?
e. What is the activity variance along the critical path?
f. What is the probability of completion of the project before week 42?
Correct Answer:

Verified
a. tₑ =
= 9 weeks
b. σ² =
² =
² = 9...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
a. tₑ =
b. σ² =
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q17: The phase of project management that takes
Q18: Table 7.13<br>All activity times for the project
Q19: Which one of the following best describes
Q20: Table 7.8<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table 7.8
Q21: Table 7.14<br>You are responsible for managing a
Q23: Figure 7.1<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Figure 7.1
Q24: Scope creep is one of the primary
Q25: Figure to accompany Table 7.7<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg"
Q26: A(n) _ identifies the key threats to
Q27: A critical path is any sequence of