Multiple Choice
Scenario 9.12
Demand = 100,000 units/year
Number of days per year = 250 weeks
Standard deviation of weekly demand = 50 units
Average lead time = 5 days
Standard deviation of lead time: 2 days
Cycle-service level = 99%
A continuous review system is used to control inventory.
-Use the information in Scenario 9.12. What is the standard deviation of demand during lead time?
A) greater than 0 but less than or equal to 500 units
B) greater than 500 units but less than or equal to 1,500 units
C) greater than 1,500 units but less than or equal to 2,500 units
D) greater than 2,500 units
Correct Answer:

Verified
Correct Answer:
Verified
Q171: As safety stock increases, the holding cost
Q172: As the service level increases, the probability
Q173: The _ is the average elapsed time
Q174: When looking at inventory management, the term
Q175: Which of the following is not a
Q177: One of the secondary levers for reducing
Q178: Scenario 9.9<br>"Gollee those cats sure go through
Q179: A _ lever is one that must
Q180: The Lemma Company manufactures and sells 10
Q181: A company governed by an EOQ system