Use the following MRP record to answer the question.
Which one of the statements concerning item LMN is True?
A) The scheduled receipt of 80 units in week 3 should be expedited so that it is finished in week 2.
B) The planned order release quantity in week 3 is 80 units.
C) The planned receipt quantity in week 6 is 30 units.
D) The projected on-hand inventory in week 8 is 70 units.