Scenario 11.1 Sunshine Manufacturing Produces Three Products: X, Y, Z. the Production

Question 44

Multiple Choice

Scenario 11.1
Sunshine Manufacturing produces three products: X, Y, Z. The production of these end items is controlled by an MRP system. Each end item X is assembled with two components of A and one component of B. Each end item of Y is assembled with two components of C and one component of A. End item Z is assembled from one unit of D and one unit of C; D is manufactured from one unit of A; and C is manufactured from one unit of B.
-Use the information in Scenario 11.1. If item C has a manufacturing lead time of two weeks, and a planned receipt of 65 units is needed in week 4, which of the following statements is True?


A) The planned order release in week 2 for item C is 130 units.
B) The gross requirements for item B in week 4 is 65 units.
C) The gross requirements for item B in week 2 is 130 units.
D) The gross requirements for item B in week 2 is 65 units.