Multiple Choice
Scenario 11.1
Sunshine Manufacturing produces three products: X, Y, Z. The production of these end items is controlled by an MRP system. Each end item X is assembled with two components of A and one component of B. Each end item of Y is assembled with two components of C and one component of A. End item Z is assembled from one unit of D and one unit of C; D is manufactured from one unit of A; and C is manufactured from one unit of B.
-Use the information in Scenario 11.1. If item C has a manufacturing lead time of two weeks, and a planned receipt of 65 units is needed in week 4, which of the following statements is True?
A) The planned order release in week 2 for item C is 130 units.
B) The gross requirements for item B in week 4 is 65 units.
C) The gross requirements for item B in week 2 is 130 units.
D) The gross requirements for item B in week 2 is 65 units.
Correct Answer:

Verified
Correct Answer:
Verified
Q39: A bill of materials is a record
Q40: What are the key inputs to an
Q41: A(n) _ is inventory carried into a
Q42: Which of the following statements about MRP
Q43: If a planned receipt for an item
Q45: _ is a lot-sizing rule under which
Q46: Gross requirements are the total demand derived
Q47: Table 11.2<br>Mutts Amazing Dogs has developed the
Q48: Complete the following MPS Record<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg"
Q49: A technique used for projecting time-phased capacity