Multiple Choice
Suppose that there are two products with the same first product time. However, product A has an improvement rate of 10% while product B has an improvement rate of 15%. How much longer will it take to make the 10th unit of product A compared to product B?
A) Both will have the identical time for the 10th unit.
B) A will take 33% more time.
C) A will take 33% less time.
D) A will take 21% more time.
E) A will take 21% less time.
Correct Answer:

Verified
Correct Answer:
Verified