Multiple Choice
The first unit of a product took 1,000 hours to build and the learning curve is 80%. Approximately how long will it take to make the next five units?
A) 4299 hours
B) 3738 hours
C) 3299 hours
D) 2738 hours
E) 562 hours
Correct Answer: