A defense contractor has just started producing engines for a new government contract. The first engine took 800 hours to produce. If the learning curve is 80%, approximately how long will it take to produce the first 20 engines?
A) 8388 hours
B) 665 hours
C) 8083 hours
D) 310 hours
E) 10,000 or more hours