A manager is trying to estimate the appropriate learning curve for a certain job. The manager notes that the first four units had a total time of 25 minutes. Which learning curve would yield approximately this result if the first unit took 9 minutes?
A) 0.70
B) 0.75
C) 0.80
D) 0.85
E) 0.90
Correct Answer:

Verified
Correct Answer:
Verified
Q42: The earliest application of learning curves appears
Q43: In the formula to compute the time
Q44: Explain how learning curves might be applied
Q45: "By tradition, learning curves are defined in
Q46: When learning curves are plotted on _
Q48: The doubling approach to learning curve calculations
Q49: Your firm has expertise with a special
Q50: A 90% learning curve implies that each
Q51: A product was priced assuming an 80%
Q52: Learning curves can be applied to a