    Lead Time for Cakes Is 2 Days with Daily Demand
Solved

Lead Time for Cakes Is 2 Days with Daily Demand

Question 101

Question 101

Multiple Choice

Lead time for cakes is 2 days with daily demand of 4 cakes and a safety stock of 1/2 day. Each container (kanban) holds 2 cakes. What is the correct number of kanbans?


A) 4
B) 1
C) 5
D) 10
E) 25

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q96: Which of the following is characteristic of

Q97: A bakery uses 5 kanban containers that

Q98: In JIT partnerships, suppliers have several concerns.

Q99: With level schedules, a few large batches,

Q100: JIT systems carry inventory just in case

Q102: TPS stands for Total Production Streamlining.

Q103: The cook in a fast-food restaurant knows

Q104: If a factory wants to cut its

Q105: Which one is NOT an application of

Q106: Characteristics of just-in-time partnerships do NOT include:<br>A)

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines