Multiple Choice
A product has annual demand of 100,000 units. The plant manager wants production to follow a four-hour cycle. Based on the following data, what setup time will enable the desired production cycle? d = 400 per day (250 days per year) , p = 4000 units per day, H = $40 per unit per year, Q = 200 (demand for four hours, half a day) , and the hourly labor rate is $18.
A) 0.40 minutes
B) 24.0 minutes
C) 7.2 minutes
D) 40.0 minutes
E) 16.0 minutes
Correct Answer:

Verified
Correct Answer:
Verified
Q70: When implemented as a comprehensive operations strategy,
Q71: Which one of the following scenarios represents
Q72: Reducing inventory exposes variability in production processes.
Q73: What does TPS stand for?<br>A) Total Production
Q74: Cross-training is a common JIT layout tactic
Q76: TPS stands for Toyota Production System.
Q77: Which of the following is generally found
Q78: How are lean operations and the Toyota
Q79: Which one of the following is NOT
Q80: Which of the following is NOT characteristic