Multiple Choice
The correct sequence from longest to smallest duration scheduling is:
A) capacity planning, aggregate planning, master schedule, short-term scheduling.
B) aggregate planning, capacity planning, master schedule, short-term scheduling.
C) master schedule, capacity planning, aggregate planning, short-term scheduling.
D) master schedule, aggregate planning, capacity planning, short-term scheduling.
E) capacity planning, master schedule, aggregate planning, short-term scheduling.
Correct Answer: