Multiple Choice
The jobs listed below need to be completed. Assume that it is now day 140. If the jobs are sequenced according to the shortest processing time rule, what is the lateness of job A?
A) 0.0 days
B) 23.0 days
C) 7.4 days
D) 9.0 days
E) 11.6 days
Correct Answer:

Verified
Correct Answer:
Verified