Multiple Choice
When a set of jobs must pass through two workstations whose sequence is fixed, ________ is the sequencing rule most commonly applied.
A) critical ratio
B) earliest due date
C) first come, first served
D) slack time remaining
E) Johnson's rule
Correct Answer:

Verified
Correct Answer:
Verified