Complete the table; find average lateness, average completion time, and average number of jobs in the system. Assume all durations are in days and that the jobs are processed at the shop in the order that they arrive (A then B then C then
D). Today is day 1.
Complete the table; find average lateness, average completion time, and average number of jobs in the system. Assume all durations are in days and that the jobs are processed at the shop in the order that they arrive (A then B then C then D). Today is day 1.

Correct Answer:

verifed

Verified

blured image Avg. lateness = 22/4 = 5.5 da...